Nvidia's reported $250B OpenAI backstop still hinges on power and a tenant
Nvidia is reportedly discussing a roughly $250 billion financing backstop that could help OpenAI lease a proposed 10GW Ohio data-center campus. But no deal has been announced, other AI companies are pursuing the federally controlled power, and the reported 800MW first phase would be only a fraction of the planned buildout.
- Nvidia is reportedly discussing a roughly $250B guarantee to support an OpenAI lease at a proposed 10GW Ohio data-center campus; it is not an announced deal.
- The site’s power allocation is a live constraint: OpenAI is interested, but Anthropic, Microsoft and Google have also discussed it with the Commerce secretary, according to the report.
- The reported 800MW first phase by 2028 equals 8% of the proposed 10GW campus, underscoring the distance between an initial build and the headline ambition.
Nvidia, the supplier of AI and accelerated-computing systems, is reportedly considering credit support for OpenAI, the ChatGPT maker, as OpenAI explores leasing an enormous proposed campus in southern Ohio. The unusual part is not simply the amount. It is that a hardware supplier could help make its prospective customer’s infrastructure debt easier to raise.
A proposed guarantee, not a completed financing
People familiar with the matter told the report that Nvidia is in talks to provide a roughly $250B backstop. The support would help OpenAI lease a 10GW data-center project being developed by SoftBank’s energy subsidiary, and could let the developer raise debt on more favorable terms than without a financial backer for OpenAI, which the report describes as an unprofitable private company without an investment-grade credit rating.
The report says the campus could cost more than $500B including chips, but it does not describe a signed lease, a final guarantee, the amount of debt to be issued, or the conditions under which Nvidia would owe money. Those omissions matter: the reported figure describes talks over potential financial support, not cash spent, debt raised or computing capacity delivered.
An account of those discussions said Nvidia was also separately discussing financing for chip purchases that could total another $350B. It attributed that detail to the earlier report; neither account establishes an agreement for that additional amount.

DOE fact sheet: plans for 10 gigawatts of new generation, including at least 9.2 GW of natural-gas generation. Source: U.S. Department of Energy.