NextDC puts community backing first as M3 delay strains expansion
NextDC is prioritising community support and contracted customers after Melbourne power delays forced a spending retreat. The risks extend to customer rights and access to debt, even as rivals take a 9.9% stake.
- NextDC is putting community support for Melbourne's M3 campus and contracted customers ahead of uncontracted expansion.
- The spending pause was already announced in October; construction of M3's existing data halls was continuing.
- Delayed power affects billing, customer rights and the conditions for drawing debt. A capital spending review is due by November 20.
Australian data centre operator NextDC made winning community support for its M3 Melbourne expansion its top priority on November 9, as chief executive and managing director Craig Scroggie reiterated the retreat from projects without customer commitments. Scroggie has led NextDC since June 2012, after serving as a director from December 2010, as documented in an ASX-filed prospectus.
NextDC supplies power, security and connectivity infrastructure to cloud providers, businesses and government. Its M3 setback exposes the gap between signing customers and being able to serve them: electricity delays have pushed back billing, reduced forecasts and left the company assessing customers' contractual remedies.
Speaking at the UBS Australasia conference, Scroggie said community backing for M3 came first and projects without customer contracts were no longer priorities, according to the conference report. He did not identify how many projects would pause. The report cited NextDC's annual report as showing 11 centres in development or planning; that is the wider pipeline, not a count of halted projects.
The retreat began before the conference
The November remarks reinforced a policy NextDC had already disclosed in its October 21 market announcement: projects without customer contracts had been paused, new developments and land purchases put on hold, and spending redirected to near-term contracted capacity. The board was also considering sales of development sites not needed soon.
M3 is an approved and partly operational campus whose later stages require further permission and power. Construction of data halls within its existing buildings was continuing. The electricity works and future expansion faced separate obstacles.
NextDC said Jemena Electricity Networks (Vic), the distributor supplying M3, had suspended parts of its 66kV line augmentation works in September. According to NextDC's account of Jemena's explanation, community opposition had created safety and site-access problems, while the local council, acting as road authority, withheld consent pending consultation. NextDC also promised a board-supervised community engagement plan for M3.