Meta Warns of Tougher Data Center Builds as States Still Seek Investment
Meta president Dina Powell McCormick expects tougher conditions for new US data centers after Democratic election victories, but says states still want investment. The test is whether electricity commitments, local jobs and tax benefits can secure community support.
- Meta expects new US data centers to face tougher scrutiny after the midterm elections.
- Its president says an unnamed governor-elect still wants talks to preserve investment and jobs.
- Meta is more optimistic about expanding existing sites and says it receives inquiries to lease its computing capacity.
Meta, the social networking company investing in AI, expects the midterm election results to complicate new US data centers. Its warning comes with qualifications: states still want the investment, and the company is more optimistic about expanding existing sites. Its case to communities rests on electricity commitments, local jobs and tax benefits.

Dina Powell McCormick in Meta’s January 2026 appointment announcement. Photo: Meta. Source: Meta.
A warning from the executive charged with financing expansion
Dina Powell McCormick, Meta’s president and vice chairman, a former Goldman Sachs partner and deputy national security adviser to President Donald Trump, delivered the warning at the WSJ Tech conference on November 4. Her remit extends directly into the problem: Meta’s January appointment announcement assigned her to work with its computing and infrastructure teams and develop capital partnerships to expand investment capacity.
She previously served on Meta’s board and spent 16 years at Goldman Sachs, including leading its sovereign investment banking business. Meta cited her financial experience and international relationships in explaining the appointment. Her role connects the financing of expansion with its impact on host communities.
She said building data centers was “going to be harder” after Democrats’ widespread victories, while acknowledging that many factors shaped the election. The conference report also described Meta as more optimistic about expanding existing sites. That distinction matters: opposition to a new location need not have the same consequences as scrutiny of an established campus.
Meta, whose social networking services already require extensive computing infrastructure, has a substantial footprint at stake. Powell McCormick said it has been building data centers for 20 years and operates in 23 states. Five states, including Texas, will have projects of at least one gigawatt, she said in the . Those are company descriptions of its footprint and plans, rather than an independently audited capacity inventory.