Industry group warns AI demand is squeezing PCB materials despite factory investment
Editorial Team
••📖8 min read
The Global Electronics Association says AI servers are absorbing scarce circuit-board materials and crowding out other industries. New factories are coming, but upstream constraints and uncertain demand complicate the response.
The Global Electronics Association expects standard circuit-board materials to remain constrained through at least the first half of 2027.
Its warning concerns access to supply across industries, as AI servers consume more materials and manufacturing time.
Suppliers are expanding, but the product mix, startup dates and risk of a demand correction complicate investment decisions.
AI infrastructure demand is crowding other electronics manufacturers out of scarce printed circuit board materials, warns the Global Electronics Association, the industry standards and advocacy organization formerly known as IPC. Its November 18 industry alert says automotive, industrial, medical, defense and telecommunications companies report longer lead times and difficulty securing supply. It considers meaningful relief unlikely before mid-2028.
The concern extends beyond chips: printed circuit boards, or PCBs, connect electronic components. More semiconductor production and final assembly cannot overcome a shortage of the boards and materials between them. Yet the warning is also a case for public support from an industry facing uncertain investment returns. The association explicitly contemplates demand correcting in 2027 if customers stop buying ahead.
The association's roots are in printed circuit boards. Its June 2025 rebranding announcement described IPC's 70-year legacy and engagement with more than 3,000 member companies; IPC remains the brand for its standards and certification programs. Its constituency spans equipment and materials suppliers, board makers, semiconductor companies and manufacturers of finished products. That gives its warning an industry-wide remit, while its members also have a stake in the incentives it seeks.
More layers compete for the same inputs
According to the association, a typical PC board has about 12 layers, while AI-server boards are moving to 40–60 layers or more. Each additional layer requires more glass fabric, resin, copper foil and laminate. Lead times for high-layer boards are running 16–20 weeks or longer, it says.
The association's explanatory note identifies glass, resin, foil and equipment as upstream constraints even as fabrication capacity expands. Its argument is that new board lines still depend on scarce inputs, so counting factories alone overstates the ability to meet demand.
There is corroboration beyond the trade body for the mechanism, though not for the full duration or scale of its forecast. Cori Masters, Gartner's senior research analyst director for Supply Chain Operations, said in that the research firm had observed upstream materials constraints for the previous couple of quarters. She said the shift toward high-layer AI boards increases throughput time and reduces line availability for traditional products.
Z.AI’s next flagship model is reportedly behind schedule as rival providers tighten distillation defenses. US licensing rules for overseas computing threaten further delays, with Moonshot forecasting longer release cycles if its access is cut off entirely. Interim releases and alternative suppliers complicate the picture.
The same account, citing the association's report, puts standard FR-4 laminate delivery times at six to eight weeks, against two to three weeks a year earlier; advanced low-loss laminates take 14–18 weeks. These are material delivery times, distinct from the lead times for finished high-layer boards.
Prices also show pressure, but their comparison periods matter. An account quoting the association's report says prepreg—resin-impregnated fiberglass used in board construction—rose about 180% in price in the year to August 2026. It gives an increase of about 140% for E-glass fabric from its third-quarter 2025 low, a different baseline. The association's more consequential claim is that paying more may not secure delivery: it says hyperscalers, the largest buyers, are reserving supply while other sectors fall behind.
The association's headline bookings figures describe North America, rather than global demand or AI boards alone. Its September statistical release draws on a representative sample of rigid PCB and flexible circuit manufacturers selling in the United States and Canada.
Measure
January–September 2026 versus the same period in 2025
September 2026 versus September 2025
PCB bookings
+56.1%
+229.4%
PCB shipments
+13.3%
−6.4%
The monthly decline qualifies the picture of rising output: shipments were up over the first nine months but down in September from a year earlier. The association identifies data centers and networking, alongside aerospace and defense programs, as demand drivers. These figures do not isolate AI's contribution or measure a global volume of unfilled orders.
The September three-month book-to-bill ratio was 1.77: the value of orders booked over three months divided by sales billed during the same period among surveyed companies. Orders were therefore running ahead of billed sales, but that does not establish how much will become lasting demand. The association cautions that bookings are more volatile than shipments and that monthly ratio changes may not be significant without a trend lasting more than three consecutive months.
The association cites industry estimates of at least $10 billion invested in new PCB plants in Southeast Asia over the past three years and at least as much in China. It says Asia makes more than 90% of the world's boards. Those investments expand fabrication; they do not by themselves resolve the upstream shortages.
Materials producers are responding too. A report on capacity expansion identifies Doosan's planned copper-clad laminate production base in Thailand and Ventec's newly opened plant there. Ventec and MICAM also plan copper-clad laminate production in Ireland aimed at European defense electronics. These are alternatives to a static supply base, although the report does not establish that they will close the market's shortfall.
Panasonic Industry, the Panasonic Group operating company supplying electronic components and materials, provides a more detailed investment timetable. Its existing MEGTRON circuit-board materials serve high-speed communications and server applications; the company says MEGTRON6 entered mass production in 2004. Its expansion therefore builds on an established materials business.
In its October 30 announcement, Panasonic Industry allocated approximately ¥67 billion to additional MEGTRON capacity in Suzhou, China, and Ayutthaya, Thailand. The investment includes approximately ¥30 billion for Suzhou's second phase and ¥37 billion for Ayutthaya's second phase. The company gives these scheduled milestones:
Circuit-board materials site
First phase
Second phase
Suzhou, China
Mass production in December 2026
Operations in August 2028
Ayutthaya, Thailand
Operations in November 2027
Operations in April 2029
Some materials output is thus scheduled before the association expects broad relief. But Panasonic's expansion targets high-performance materials for AI servers, and its announcement does not quantify how far it will relieve shortages for conventional electronics customers. The ¥67 billion is the circuit-board materials portion of a wider ¥92 billion package that also covers capacitors and semiconductor-packaging materials research; the whole package should not be counted as PCB materials capacity.
Other bottlenecks have longer schedules. The capacity report says copper-foil producer Mitsui Kinzoku's new Malaysian plant is not due to start production until April 2031. It also cites PCB supplier Confidee's Didrik Bech describing glass fabric as supplied by only a handful of major manufacturers worldwide, with no capacity increase expected before late 2027 at the earliest. That is a supplier's assessment, rather than a comprehensive capacity inventory.
Expansion is also following a changing product mix. Market researcher Yole's projections, cited in the report, put annual growth through 2031 at 15.7% for boards with at least 18 layers, versus 2.3% for four-to-six-layer boards. Those forecasts indicate why growth in overall PCB capacity need not translate into equal access for every customer segment.
What would establish the scale of the crisis?
The association says the exposure could rival the 2021 chip shortage. That comparison describes the risk of a basic input interrupting production across industries; it is not a quantified forecast of equivalent losses.
A January 2022 US Department of Commerce bulletin offers a concrete benchmark for the earlier crisis. Reporting a voluntary supply-chain information request with responses from more than 150 companies, it said median chip inventory had fallen from 40 days in 2019 to less than five days. The PCB warning supplies no directly comparable inventory measure. Its regional bookings and lead-time evidence cannot establish equivalent economic damage.
For buyers, the immediate decisions are whether to commit volumes and qualify alternative materials and suppliers. The association recommends sharing realistic forecasts and avoiding duplicate orders. Qualification requires testing and customer approval, so an alternative material's existence does not mean it can immediately enter production.
For governments, the association seeks lead-time monitoring, faster permitting, investment incentives for advanced PCB and substrate manufacturing, and funding for research and materials qualification. It also wants priority allocation for defense, aerospace, medical and critical infrastructure programs, plus targeted grants and loan guarantees to protect critical programs and small fabricators through a possible downturn. These are requests, not enacted measures.
Regional investment has its own tension. The association puts Europe's share of global PCB production at 2.2% in 2023, down from 13.8% in 2000. The capacity report describes closures and insolvency alongside new projects, and identifies long-term customer volume commitments as important to further European investment. A global shortage does not ensure that every regional producer will prosper.
The next evidence needed is whether scheduled materials plants actually start, whether customers qualify alternatives, and whether delivery times shorten for conventional electronics users. Sustained shipments, rather than bookings alone, will help determine how much capacity buyers and governments should finance—and how much support would still be justified if advance orders unwind.
Capita is seeking fresh equity and creditor support after replacing its chief executive. Pension recovery costs are only part of its profit downgrade, while government figures show unresolved cases still growing.
Provisional CBS figures show AI use more than doubled among Dutch businesses with at least two workers in 2026. Text generation spread rapidly, while reported productivity gains leave the size of the economic payoff unresolved.
Google says Gemini Live’s Guided Vision is available on iOS, extending visual descriptions and spoken camera-framing help to iPhone users. Device eligibility and regional coverage remain unclear, and Google warns against using it for navigation.
The Dutch government wants Congress to keep the MATCH Act out of its annual defence bill. The proposal would tighten controls on ASML’s China business, including servicing, despite existing Dutch restrictions on advanced chipmaking equipment.
The London startup’s pre-seed round backs research and testing for patient-facing AI. Its founders bring medical-device deployment experience, but benchmark findings and customer submissions do not yet establish real-world safety.
Switzerland’s cybersecurity chief says five confirmed AI-agent attacks affected businesses including three critical-infrastructure operators. Four attacks breached systems, but no major outages were reported, and the public evidence leaves the attackers and specific consequences unknown.
SemiAnalysis reports that Amazon’s Trainium3 delivers up to 2.28 times the tokens per modeled dollar of Nvidia’s GB300 NVL72 in an AgentX preview. The result expands public evidence for custom AI chips, but validation, model matching and customer pricing still determine its practical value.
Microsoft says Chinese and North Korean hacking groups have adopted ARTEX, an AI penetration-testing framework that coordinates existing tools. Its spread across models and software forks complicates efforts to contain abuse through a single provider.
Neuralink says its LINK pivotal study is recruiting people with severe paralysis from ALS to assess digital device control, daily independence and long-term safety. Earlier participant gains and technical setbacks frame the test; the implant remains investigational.
India’s IT secretary says Sarvam’s commercial hosting of foreign AI models does not conflict with its publicly supported domestic model development. Eligibility for proposed inference support remains unresolved.
Manufacturing partners have reportedly told buyers that Nvidia will not permit server orders to ship to Malaysia, Singapore, Thailand and Indonesia as they assess new US export controls. The uncertainty is already reaching cloud-project financing.
Trustly’s existing owners are funding new AI payment products after job cuts. New quarterly results show rising payment volumes and revenue, but weaker earnings than a year earlier.
The Pentagon denies reports that officials weighed production powers to pressure Nvidia to restore Jensen Huang. Nvidia confirms senior government input, but its board’s foreign-intelligence investigation remains open.
Perplexity says users are choosing Google's new model over rival offerings, with daily token volume doubling in three days. The 120-billion figure is cumulative, and the early demand leaves retention and task economics unresolved.
Kioxia says a proof of concept paired Nvidia software with about 1.1 PB of raw SSD capacity to expand the datasets GPUs can access. The demonstration establishes a capacity proposition, while workload performance and deployment economics remain undisclosed.
Google’s November 25 update adds Familiar Face alerts and remote siren controls to two Walmart Onn outdoor cameras. The expansion makes inexpensive Nest alternatives more capable, while the value depends on subscription access and reliable video playback.
OpenAI is testing a combined Chat and Work experience with a small group of Pro subscribers. A shared allowance arriving more broadly in December will put advanced conversations and delegated tasks on the same budget, but the size of any resulting loss of access remains unknown.
Sellers are seeking buyers for thousands of Nvidia B300 chips, while Asian data centers try to replace Chinese customers affected by U.S. controls. Rental prices have fallen, but short contracts remain scarce and operators face demanding financing terms.
Lenders are delaying or reassessing financing for Asian data centers serving Chinese technology firms as new US licensing rules put chip purchases and customers’ access to computing capacity in doubt.